——并联加设分解炉炉体并优化预热器部分结构提产40%以上
一、 技改出发点:在分解炉再不能加高加粗而上部预热器还有提产空间的前提下,若要再次提高产量,只能首先提高炉容,可在原炉体旁边外挂并联新炉体以增加分解炉的总容积。
二、 具体方案(在其它设备特别是篦冷机能力足够的前提下)
1、 加设并联分解炉炉体;
2、 C5筒进风口、C4筒进风口继续往上扩大,将这两级旋风筒顶盖扩大为上旋螺旋面;
3、 生料制备与煤粉制备系统若能力不够,可再分别并联小规格立磨补充产量;
三、 Φ4.7m*74m窑实际技改结果:
1、 熟料产量已达到7000t/d;
2、 垃圾协同处理量达到700t/d.
山东绿工新材料科技有限公司
公司网站:www.lgxcltech.com
公司公众号:绿工新材料
Tel:(+86)18353360679
New technologies for greatly saving energy, reducing consumption and increasing production of cement kiln with calciner system
——The calciner connected in parallel with external double furnace body,which make the clinker output increased by more than 40%
Ⅰ Starting point of technical transformation: on the premise that the precalciner can no longer be raised and roughened, and the upper preheater still has room to increase the production, if we want to increase the production again, we can only increase the furnace capacity first, and we can add a new furnace body in parallel next to the original furnace body to increase the total volume of the precalciner.
Ⅱ Specific plan(Under the premise of sufficient capacity of other equipments, especially grate cooler)
1、The parallel decomposing furnace body is added;
2、The inlet of C5 cyclone and C4 cyclone continued to expand upward, expanding the two-stage cyclone top cover into an upward spiral surface;
3、If the capacity of raw material preparation and pulverized coal preparation system is not enough, the parallel small-scale vertical grinding can be used to supplement the output.
Ⅲ Actual technical reform results of Φ4.7m * 74m kiln
1、The output has upto 7000t/d;
2、The collaborative treatment capacity of garbage reaches 700t /d

Shandong Green Engineering New Materials Technology Co.,Ltd
Company website: www.lgxcltech.com
Email: gudaofa@163.com
Wechat:gudaofa
联系人:绿工新材料
手机:+86 18353360679
电话:+86 13953348649
邮箱:gudaofa@163.com
地址: 山东省淄博市张店区马尚街道办事处心环东路6号润德大厦B座1109室